Location
Izmir


Country
Türkiye


Client
Izmir Metropolitan Municipality


Contractor


Features / Capacity / Area
11 km / 14 Station, Depot and Parking Site ve 336 m long Viaduct


Contract Date
2017 June

Within the scope of the Cigli Tram Line, which will operate integrated with the existing Karsiyaka Tram, there are 14 stations and a depot/parking area with a capacity of 13 vehicles. In addition, a 336 m long and 12,95 m wide tram viaduct was designed to ensure safe passage of the line over the ring road.

 

Concept, preliminary and final projects and tender documents of the tram line have been prepared.

 

The work carried out within the scope of work is as follows;

  • Preparation of design handbooks
  • Transportation and track study report
  • Track projects
  • Earthquake survey report
  • Financial and economic feasibility study, sensitivity analysis, cost-benefit analysis (cba)
  • Historical sites report
  • Building stock risk analysis
  • Geological site studies
  • Architectural (interior and exterior, finishing works, details, passenger analysis),
  • Structure and geotechnical design,
  • Electrical and mechanical ınstallation, mv, radio, cctv, announcement simulations, CFD, SES, piston effect simulations, medium voltage traction and catenary system, traffic, fire fighting and evacuation design
  • Drainage and infrastructure,
  • Landscape and urban renewal
  • Preparation of tender documents and quantities, quantities and unit price descriptions.